From the front door of my office trailer, circa early February 2012:
We were hanging steel and running underground drain lines in late February. We were extremely lucky with the mild winter weather this year:
By mid-March, we were erecting more and more sections of the building:
In early April, the boilers started arriving:
Our piping fabrication facility starting pumping out some of the large-bore spools and delivering to site around the same time:
Itsy bitsy hole for the main process drain sump pit and lift pump station. What's cool about this hole is that it required dynamite to get through nearly 9' of bedrock to achieve the depth we needed:
It’s not every day you get to drive a road grader inside a building:
Flying the first sections of cooling towers to the roof of the Refrigeration Building:
A few days later the upper sections arrived:
Not your average PVC sprinkler pipe going in below grade… This is the main inlet piping for that process drain system going into the pump pit and lift pump station:
We fabricated this 80,000 gallon tank on site – the walls are ½â€